Here is what hopefully will be the last major one before summer, started getting a few things done on the van over the last month.

The storage unit above the kitchen is nearly finished, the curtains are finished and up, I've ordered all the bedding, tested the water supply/boiler, done some more trim, and done the facing on the kitchen unit.

So what needs done still? For the build, I've done a 'To Do' list... hopefully once these are done it will be ready to use... in 4 weeks time!

Services
  • Kitchen Sink Drainage
  • Seal Shower
  • Test for Gas Leaks
  • Fit Solar Panels & Wiring
  • Split Charge/Fridge Wiring

Structural
  • Finish Overhead Locker
  • Build Gas Bottle Locker

Miscellaneous
  • Lay Flooring
  • Tint Back Window

There are still things to be done externally, such as fix a few rusty spots, windscreen re-seal and get it serviced, but these aren't essential for me to be able to use it.